Wyndham Grand Batumi Gonio. Family Club. Block A 1. Plastering works, 2, 5 floors. — Plastering of walls, 5th floor. — Plastering of soffits, 4th floor. 2. Facade works. — Facade insulation, mineral wool reinforcement layer. — Cladding of the facade with clinker tiles. 3. Plasterboard frame construction. Installation of partitions. Works on territory improvement. 1. Arrangement of fence foundation. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Plastering works, 2, 5 floors.
— Plastering of walls, 5th floor.
— Plastering of soffits, 4th floor.

2. Facade works.
— Facade insulation, mineral wool reinforcement layer.
— Cladding of the facade with clinker tiles.

3. Plasterboard frame construction.
Installation of partitions.

Works on territory improvement.
1. Arrangement of fence foundation.