Elite Family Residence 1. Finishing works. — Installation of the moldings, the 4th floor. — Painting on the staircases and in the units, the 1st floor. — Porcelain stoneware installation in units, penthouses. — Marble facing installation on the staircases. 2. Facade works. — Cladding the facade with natural stone. — Installation of the railings of the central facade. 3. Plumbing. Installation of final plumbing fixtures in units. 4. Wiring — Installation of electrical panels in units. -Installation of heating boilers. -Installation of lighting in the elevator shaft. 5. Installation of staircases railings. 6. Installation of the drywall frame. Drywall installation for elevator gantries. 7. Installation of the drywall frame. — Cladding of elevator shaft openings with drywall. - European Village

Elite Family Residence

1. Finishing works.
— Installation of the moldings, the 4th floor.
— Painting on the staircases and in the units, the 1st floor.
— Porcelain stoneware installation in units, penthouses.
— Marble facing installation on the staircases.

2. Facade works.
— Cladding the facade with natural stone.
— Installation of the railings of the central facade.

3. Plumbing.
Installation of final plumbing fixtures in units.

4. Wiring
— Installation of electrical panels in units.
-Installation of heating boilers.
-Installation of lighting in the elevator shaft.

5. Installation of staircases railings.

6. Installation of the drywall frame.
Drywall installation for elevator gantries.

7. Installation of the drywall frame.
— Cladding of elevator shaft openings with drywall.