Elite Family Residence 1. Finishing works. — Painting in the units, the 1st, , 2nd floors. — Painting in the common areas. — Painting on the staircases. — Tiling in the bathrooms, the 5th floor. 2. Facade works. Cladding with the natural stone. 3. Waterproofing. — On the balconies. 4. Installation of insulation systems and winterization of the terraces. 5. Mockup installation. Furniture assembling. - European Village

Elite Family Residence

1. Finishing works.
— Painting in the units, the 1st, , 2nd floors.
— Painting in the common areas.
— Painting on the staircases.
— Tiling in the bathrooms, the 5th floor.

2. Facade works.
Cladding with the natural stone.

3. Waterproofing.
— On the balconies.

4. Installation of insulation systems and winterization of the terraces.

5. Mockup installation.
Furniture assembling.